WORK IN PROGRESS – 1ÈRE PARTIE

June 2023 – Location, Location, Location…

First step: find a plot large enough, well-oriented, in a quality and secure development, and close to the Medina. After several visits, our choice was clear. We would be next to Golf Amelkys, barely 4km from the Koutoubia and Jemaa El-Fna square!

Selected plot near Golf Amelkys

March 2024 – Building Permit Obtained

Passionate about travel, architecture, and decoration, constantly seeking well-being and positive energy, we first wanted to build our dream family home that reflects who we are, to spend vacations in an incredible region. Over time, through reflection and encounters, we wanted to go further and give meaning to our project. This is how we designed a hybrid space between an exceptional villa, ecolodge, solidarity shop, art gallery, relaxation and wellness areas, workshops and even a restaurant, always with one guiding principle: to offer our guests and friends an exceptional, timeless experience, respecting the environment and local communities. La Villa 58 was born.

The project was submitted and the building permit granted — construction could begin.

August 2024 – Construction Begins

08/2024

Site preparation

Implantation 08/2024 Implantation 08/2024

09/2024

Foundations and ground floor slab pouring

Fondations 09/2024 Dalle RDC 09/2024 Coulage dalle 09/2024

10/2024

First columns raised. Beams and hollow blocks installed before first floor pouring

Poteaux 10/2024 Poutrelles 10/2024 Marmites 10/2024

11/2024

First floor slab poured, master suite columns raised. Wall elevation and insulation

Dalle R+1 11/2024 Murs 11/2024 Isolation 11/2024 Élévation 11/2024

12/2024

Pool construction underway…

Piscine 12/2024 Piscine 12/2024

01/2025

First Essaouira stones laid – Thank you and bravo Younés!

Pierres Essaouira 01/2025 Younés 01/2025 Pierre posée 01/2025 Façade 01/2025

02/2025

Large plant installation. 6,500-liter cistern installed. Tadelakt on boundary walls

Plantation 02/2025 Citerne 02/2025 Tadelakt 02/2025 Clôtures 02/2025

03/2025

Hedges, fruit trees and pool coconut palms planted… Meanwhile, inside the house, the electrician, plumbers and plasterers are hard at work…

Haies 03/2025 Cocotiers 03/2025 Intérieur 03/2025 Électricité 03/2025 Plomberie 03/2025 Plâtrerie 03/2025

05/2025

Floor screed poured and tiles laid! Meanwhile, outside, first sunshades installed… and agaves and euphorbias planted at the entrance…

Chape 05/2025 Carrelage 05/2025 Thé menthe 05/2025 Brise-soleils 05/2025 Pierre Younés 05/2025 Carrelage sol 05/2025 Brise-soleil extérieur 05/2025 Agaves 05/2025 Euphorbes 05/2025 Entrée 05/2025 Vue extérieure 05/2025 Terrasse 05/2025 Piscine vue 05/2025 Jardin 05/2025 Vue d'ensemble 05/2025

Construction continues at a good pace… delivery expected early September. Furnishing and decoration to follow for the first bookings late 2025, early 2026! See you soon…